I-15, Black Ridge to the Iron County Line
Contract: W.W. Clyde & Co.
Amount: $17,338,995
Location: Between the Toquerville and New Harmony exits.
Impact: * Lanes shift to accommodate work in the median.
* Single lane closures in the event of bridge deck repairs.
* Potential single lane closures and reduced speeds in the southbound lanes Monday through Friday from 7:00 p.m. to 11:00 a.m.
Activity: * Potential bridge deck repairs.
* From milepost 33 to 42 the contractor is installing new fence.
* Workers are installing conduit from mileposts 35 to 37.
* Heavy equipment operators are excavating and moving material in the median and shoulders adjacent to northbound lanes at mileposts 34 through 38.
* Retention wing walls are being erected under the structure at Exit 36.
* Workers are replacing parapets at the Exits 40 and 42.
* A box culvert is being extended at milepost 42. .
I-15, Dixie Drive Interchange
Contract: Washington County Constructors
Amount: $52,549,452
Location: St. George (Mileposts 5 – 6)
Impact: * Two lanes of traffic remain open in both directions.
* All exits are open.
* Speed is reduced to 55 m.p.h.
* Northbound traffic has been shifted to the southbound side of the interstate near the Santa Clara bridge.
* Motorists should use caution near the Bluff Street Interchange merge lanes.
* Traffic lanes have been shifted on Hilton Drive.
* The Hilton Drive Trail is closed.
Activity: * Bridge deck work over Convention Center Drive and the new northbound I-15 bridge over the Santa Clara River.
* Structural preparation for the future southbound on-ramp.
* Completing retention walls for current construction phase.
* Drainage work at Hilton Drive.
* Flood debris removal and dredging.
http://www.udot.utah.gov/i15dixie/
S.R. 212, Telegraph Street
Contract: Interstate Rock Products
Amount: $5,515,140
Location: City of Washington, 500 West to 300 East
Impact: * Traffic shifts to the south side of the road.
* Reduced speeds.
* One lane of traffic in each direction.
Activity: * Box culvert installation.
* Storm drain installation from 300 West to 300 East.
* Removing curb and gutter.
* Road milling on the north side of the road from 300 West to 100 West.
S.R. 9, 300 West To 800 North Hurricane
Contract: Interstate Rock Products
Amount: $10,203,871
Location: Hurricane City State Street
Impact: From 100 East to 800 North, traffic runs one lane on each side of the road, leaving the inside lanes closed to accommodate work on the center islands.
Activity: * Workers are building island medians and working on associated landscaping and enhancements.
* Final pavement remains.