Iron County
S.R. 130 North Cedar Main Street
Contract: Intermountain Slurry Seal
Amount: $181,181
Location: Nichols Canyon Drive to Maxwell Road
Impact: * This will be a moving operation but temporarily impact some accesses.
* Ramps at the Enoch/Minersville Exit 62 will temporarily shut down as the operation passes over the structure. Local traffic may want to consider alternate routes for convenience.
Activity: * Applying a slurry seal coat Wednesday and Thursday
* Painting is anticipated Thursday.
Washington County
I-15, Black Ridge to the Iron County Line
Contract: W.W. Clyde & Co.
Amount: $17,338,995
Location: Between the Toquerville and New Harmony exits.
Impact: * Single lane closures both directions at the New Harmony exit.
* Lane shifts to accommodate paving and grading.
Activity: * Bridge deck repairs at Exit 42.
* Excavation and ramp work near Exit 36.
* Paving inside northbound lane from mileposts 34 to 37.
* Sub-grade work on the northbound outside lane.
* Northbound retaining wall construction.
* Placing pre-cast barrier.
I-15, Dixie Drive Interchange
Contract: Washington County Constructors
Amount: $52,549,452
Location: St. George (Mileposts 5 – 6)
Impact: * Two lanes of traffic remain open in both directions.
* All exits are open.
* Speed is reduced to 55 m.p.h.
* Northbound traffic has been shifted to the southbound side of the interstate near the Santa Clara bridge.
* Motorists should use caution near the Bluff Street Interchange merge lanes.
* Traffic lanes have been shifted on Hilton Drive.
* The Hilton Drive Trail is closed.
Activity: * Pouring concrete.
* Paving.
* Retention walls west of I-15 and also under the Bluff Street Interchange.
* Structural preparation for the future southbound on-ramp.
* Drainage work at Hilton Drive.
* Flood debris removal and dredging.
http://www.udot.utah.gov/i15dixie/
S.R. 212, Telegraph Street
Contract: Interstate Rock Products
Amount: $5,515,140
Location: City of Washington, 500 West to 300 East
Impact: * Traffic lanes weave through the project.
* Reduced speeds.
* One lane of traffic in each direction.
* Sidewalk closures.
Activity: * Storm drain installation.
* Road widening.
* Retaining wall installation near 400 West.
* Utility work and landscaping.
S.R. 59, Arizona State Line to Apple Valley
Contract: A-T Asphalt Paving
Amount: $1,998,101
Location: Mileposts 0 to 11
Impact: * Oversized loads restricted.
* Pilot car operations with delays of up to 15 minutes.
Activity: Setting up traffic control and project equipment.
S.R. 9, 300 West To 800 North Hurricane
Contract: Interstate Rock Products
Amount: $10,203,871
Location: Hurricane City State Street
Impact: Expect single lane closures.
Activity: * Paving side streets.
* Painting stripes.
Southern Parkway Advanced Traffic Management
Contract: Transcore ITS
Amount: $370,674
Location: S.R. 7 Mileposts 0 to 7
Impact: No traffic impacts.
Activity: Fiber optic installation, junction boxes, camera foundations.