Various Counties
I-15, Cable Barrier & Guardrail
Contract:
Meadow Valley Contractors (Multiple Locations)
Amount:
$2,815,200
Location:
Southern Utah
Impact:
* Shoulder closures – No significant traffic impact.
Activity:
* Installing cable barrier.
* Installing guardrail.
Washington County
I-15, Black Ridge to the Iron County Line
Contract:
W.W. Clyde & Co.
Amount:
$17,338,995
Location:
Between the Toquerville and New Harmony exits.
Impact:
* Consecutive lane closures at Exits 40 and 42.
* Lane merging slow downs.
* Lane shifts to accommodate paving and grading and structural work.
* Nightly lane closures.
Activity:
* Paving
* Drainage structures from mileposts 36 to 38 northbound.
* Preparing new pavement section at New Harmony and Kolob Canyon Exits.
* Fence and sign installation.
I-15, Dixie Drive Interchange
Contract:
Washington County Constructors
Amount:
$52,549,452
Location:
St. George (Mileposts 5 – 6)
Impact:
* Two lanes of traffic remain open in both directions.
* All exits are open.
* Speed is reduced to 55 m.p.h.
* Northbound traffic has been shifted to the southbound side of the interstate near the Santa Clara bridge.
* Traffic lanes have been shifted on Hilton Drive.
* The Hilton Drive Trail is closed.
Activity:
* Retention walls west of I-15.
* Flood debris removal and dredging.
* Electrical line work.
* Paving preparation on Convention Center Drive
http://www.udot.utah.gov/i15dixie/
S.R. 212, Telegraph Street
Contract:
Interstate Rock Products
Amount:
$5,515,140
Location:
City of Washington, 500 West to 300 East
Impact:
* Traffic lanes weave through the project.
* Reduced speeds.
* One lane of traffic in each direction.
* Sidewalk closures.
Activity:
* Storm Drain installation on west end.
* Backfilling at bridge.
* Sub-grade work from Main to 300 East.
* Installing curb and gutter near Main Street.
S.R. 59, Arizona State Line to Apple Valley
Contract:
A-T Asphalt Paving
Amount:
$1,998,101
Location:
Mileposts 0 to 11
Impact:
* Oversized loads restricted.
* Pilot car operations with delays of up to 15 minutes.
Activity:
* Paving.
Southern Parkway Advanced Traffic Management
Contract:
Transcore ITS
Amount:
$370,674
Location:
S.R. 7 Mileposts 0 to 7
Impact:
* No traffic impacts.
Activity:
* Fiber optic installation, junction boxes, camera foundations.
Carbon County
S.R.10 South Price to Stake Farm Road
Contract:
Nielson Construction
Amount:
$1,840,710
Location:
South of Price
Impact:
* No major impacts expected.
Activity:
* Construction Preparation.
* Work will begin on the south end near Stake Farm Road
* Construction Open House June 23rd from 4 to 7 p.m. at the Holiday Inn in Price.
Emery County
U.S. 6, Milepost 272 To Woodside
Contract:
Nielson Construction
Amount:
$3,869,924
Location:
22 Miles north of Green River
Impact:
* Narrow lanes. One in each direction.
Activity:
* Paving.
Grand County
I-70, Yellowcat to West Cisco
Contract:
Geneva Rock
Amount:
$2,255,629
Location:
East of Thompson Springs Welcome Center
Impact:
* Single lane closures in both directions.
Activity:
* Paving.