Weekly Construction Update June 17

road construction

Various Counties

I-15, Cable Barrier & Guardrail

Contract:

Meadow Valley Contractors (Multiple Locations)

Amount:

$2,815,200

Location:

Southern Utah

Impact:

* Shoulder closures – No significant traffic impact.

Activity:

* Installing cable barrier.

* Installing guardrail.

Washington County

I-15, Black Ridge to the Iron County Line

Contract:

W.W. Clyde & Co.

Amount:

$17,338,995

Location:

Between the Toquerville and New Harmony exits.

Impact:

* Consecutive lane closures at Exits 40 and 42.

* Lane merging slow downs.

* Lane shifts to accommodate paving and grading and structural work.

* Nightly lane closures.

Activity:

* Paving

* Drainage structures from mileposts 36 to 38 northbound.

* Preparing new pavement section at New Harmony and Kolob Canyon Exits.

* Fence and sign installation.

I-15, Dixie Drive Interchange

Contract:

Washington County Constructors

Amount:

$52,549,452

Location:

St. George (Mileposts 5 – 6)

Impact:

* Two lanes of traffic remain open in both directions.

* All exits are open.

* Speed is reduced to 55 m.p.h.

* Northbound traffic has been shifted to the southbound side of the interstate near the Santa Clara bridge.

* Traffic lanes have been shifted on Hilton Drive.

* The Hilton Drive Trail is closed.

Activity:

* Retention walls west of I-15.

* Flood debris removal and dredging.

* Electrical line work.

* Paving preparation on Convention Center Drive

http://www.udot.utah.gov/i15dixie/

S.R. 212, Telegraph Street

Contract:

Interstate Rock Products

Amount:

$5,515,140

Location:

City of Washington, 500 West to 300 East

Impact:

* Traffic lanes weave through the project.

* Reduced speeds.

* One lane of traffic in each direction.

* Sidewalk closures.

Activity:

* Storm Drain installation on west end.

* Backfilling at bridge.

* Sub-grade work from Main to 300 East.

* Installing curb and gutter near Main Street.

S.R. 59, Arizona State Line to Apple Valley

Contract:

A-T Asphalt Paving

Amount:

$1,998,101

Location:

Mileposts 0 to 11

Impact:

* Oversized loads restricted.

* Pilot car operations with delays of up to 15 minutes.

Activity:

* Paving.

Southern Parkway Advanced Traffic Management

Contract:

Transcore ITS

Amount:

$370,674

Location:

S.R. 7 Mileposts 0 to 7

Impact:

* No traffic impacts.

Activity:

* Fiber optic installation, junction boxes, camera foundations.

Carbon County

S.R.10 South Price to Stake Farm Road

Contract:

Nielson Construction

Amount:

$1,840,710

Location:

South of Price

Impact:

* No major impacts expected.

Activity:

* Construction Preparation.

* Work will begin on the south end near Stake Farm Road

* Construction Open House June 23rd from 4 to 7 p.m. at the Holiday Inn in Price.

Emery County

U.S. 6, Milepost 272 To Woodside

Contract:

Nielson Construction

Amount:

$3,869,924

Location:

22 Miles north of Green River

Impact:

* Narrow lanes.  One in each direction.

Activity:

* Paving.

Grand County

I-70, Yellowcat to West Cisco

Contract:

Geneva Rock

Amount:

$2,255,629

Location:

East of Thompson Springs Welcome Center

Impact:

* Single lane closures in both directions.

Activity:

* Paving.

Free News Delivery by Email

Would you like to have the day's news stories delivered right to your inbox every evening? Enter your email below to start!

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.